South Lafourche Levee District Board of Commissioners public meetings in 2021
11 substantive meetings from 2021, with official agendas or minutes and plain-English summaries.
South Lafourche Levee District Board of Commissioners
The South Lafourche Levee District Board will vote on awarding a $2,292,660 contract for Phase II of the D-South Floodwall Improvements and consider multiple change orders and pay requests related to Hurricane Ida repairs. The board will also discuss FEMA claim denials, debris removal, and personnel changes.
- Recommendation to award $2,292,660 contract to Sealeve Construction for D-South Floodwall Phase II
- Change Order No. 13 for $1,782,868.23 for Grand Bayou Floodgate Structure (Hurricane Ida)
- FEMA denial of claim on A-East vinyl sheet piles for Hurricane Barry 2019
- Bid results for Hurricane Ida storm damage repairs to pump stations, floodgates, main office, and mechanic shop
- Personnel actions: create Operating Engineer 3 position, move Ryan to that role, hire Rod Cheramie as Operating Engineer 1
South Lafourche Levee District Board of Commissioners
The Board of Commissioners will review several engineering pay requests and emergency storm-related agreements following Hurricane Ida. The agenda includes discussions on debris removal, FEMA reimbursements, and various levee improvement projects.
- Resolution No. 2021-02 regarding Grand Bayou 'Reggie Bagala' Floodgate
- D-South Floodwall Improvements Phase I pay requests totaling $371,157.40
- Grand Bayou Floodgate Structure pay requests and change orders
- Authorization for Board President to approve emergency storm-related agreements for Hurricane Ida
- Litigation update regarding Jason Adams, et al v. SLLD
South Lafourche Levee District Board of Commissioners
The Board of Commissioners will review hurricane recovery efforts, including an emergency declaration for Hurricane Ida and storm debris contracts. The meeting includes discussions on intergovernmental agreements for the Reach L Levee Lift and Larose floodwall, as well as various engineering pay requests.
- Emergency Declaration regarding Hurricane Ida
- Review of Reach L Levee bid results
- Pay Request No. 6 for Section F Levee Improvements in the amount of $172,268.25
- Pay Request No. 40 for B-North & B-South Levee Improvements in the amount of $535,009.61
- Sale of Vinyl Sheet Piles bid results approval
South Lafourche Levee District Board of Commissioners
The South Lafourche Levee District Board will discuss and potentially approve several levee improvement projects, including a $1.8 million capital outlay and an intergovernmental agreement for Section F Berm. The board will also consider multiple engineering pay requests totaling over $1 million and personnel changes such as promotions and a new hire. The meeting covers audit updates, hurricane protection improvements, and funding for the Larose Lock.
- Approval to sign GOMESA BA-250 Intergovernmental Agreement for Section F Berm
- Capital Outlay Funding - $1.8M
- Pay Request No. 5 for Section F Levee Improvements: $64,953.33
- Pay Application No. 2 for D-South Floodwall Improvements: $291,958.75
- Personnel actions: promote Chase Berthelot, hire Robbie Savoie, create Levee Foreman A position
South Lafourche Levee District Board of Commissioners
The Board of Commissioners will review engineering reports regarding multiple levee and floodwall projects, including pay requests for Section E-North and Section F improvements. The meeting also includes discussions on NFIP mapping, Grand Bayou Floodgate updates, and insurance renewal quotes.
- Pay Request No. 14 for Section E-North Levee Improvements in the amount of $45,347.15
- Pay Application No. 1 for D-South Floodwall Improvements in the amount of $500,113.25
- Pay Request No. 9 for Golden Meadow Pump Station Floodwall in the amount of $129,027.10
- Change Order No. 10 for Grand Bayou Floodgate Structure (Floodwall & Receiving Structure) totaling a -$7,827.00 credit
- Authorization for Board President to accept the highest bid for the sale of surplus sheet piles
South Lafourche Levee District Board of Commissioners
The Board of Commissioners is reviewing several infrastructure updates, including a proposed $576,000 road project at PS No. 7. The meeting includes discussions on levee elevation agreements, water usage, and various engineering pay requests for floodwall and pump station improvements.
- Proposed PS No. 7 road from Delta Farms with an estimated cost of $576,000
- GOMESA Projects FY 2022 funding including Section F Berm ($1M) and Larose Floodwall Vessel Impact Barrier ($1M)
- Engineering pay request for Grand Bayou Floodgate Structure at $607,222.75
- Engineering pay request for Barge Floodgate Structure at $823,976.91
- Larose Floodwall Height Improvements West End A-Ph 5 pay request of $251,343.87
South Lafourche Levee District Board of Commissioners
The Board of Commissioners will consider adopting millage rates of 4.86 and 5.00 mills for 2021. The meeting includes several pay requests and change orders for levee improvements and floodgate projects. The board will also discuss bid recommendations for the D-North Ramp.
- Resolution 21-01 to adopt 4.86 and 5.00 mills for 2021
- Pay Request No. 16 for Grand Bayou Floodwall & Receiving Structure: $612,202.40
- Pay Request No. 7 for Grand Bayou Barge Floodgate Structure: $874,625.84
- Pay Application No. 5 for Reach K material delivery: $364,536.85
- GIS Engineering Amendment No. 2 for A-East Bayou Lafourche Water Retention: $18,000
South Lafourche Levee District Board of Commissioners
The South Lafourche Levee District Board will vote on multiple pay requests and change orders for levee and floodgate projects, including a $1.3 million payment for the Grand Bayou Floodgate Structure. They will also discuss pipeline crossing agreements for the A-East Bayou Water Retention project and set millages for 2021. Other business includes approval of minutes, reports, and hiring of summer laborers.
- Pay Request No. 14 for Grand Bayou Floodgate Structure: $1,299,482.19
- Pay Request No. 2 for Section F Levee Improvements (Onshore Materials): $205,237.77
- Change Order No. 1 for Golden Meadow Boat Launch Ramp: $16,535.15 (additional fill and 45-day extension)
- Approval of pipeline crossing agreements for A-East Bayou Water Retention project
- Discussion of SLLD Millages for 2021
South Lafourche Levee District Board of Commissioners
The Board of Commissioners will discuss the FY 2022 proposed budget and various engineering reports. The meeting includes reviewing multiple pay requests and change orders for levee improvements and flood protection projects.
- Review of FY 2022 Proposed Budget
- Change Order No. 2 for Section E-North Levee Improvements ($270,120)
- Pay Request No. 12 for Grand Bayou Bypass Channel Emergency Efforts ($475,556.03)
- Pay Application No. 3 for Reach K Levee Spoil material ($476,431.65)
- Update on pending litigation: Jason Adams, et al v. SLLD
South Lafourche Levee District Board of Commissioners
The Board of Commissioners is reviewing engineering reports, pay requests, and contract changes for various levee and pump station improvements. The agenda includes discussions on floodwall elevations, maintenance quotes, and emergency rehabilitation efforts following hurricanes.
- Bid opening results for D-South (Crawfish Farm) Floodwall Improvements with a recommended award of $1,648,822.00 to Sealevel Construction
- Change Order No. 1 for Leon Theriot Lock South Gate Maintenance adding $41,996.99
- Pay Request No. 4 for Golden Meadow Pump Station Floodwall in the amount of $199,668.62
- Change Order to add a stiffener plate to the GM Pump Station floodwall for $26,000
- Review of various pay requests for levee improvements and emergency rehabilitation projects
South Lafourche Levee District Board of Commissioners
The South Lafourche Levee District Board will consider approval of minutes, election of officers, and a series of engineering reports with multiple pay requests and contract amendments. Notable actions include authorizing a hunting/fishing lease bid, obtaining pump repair estimates, and approving personnel reallocations. The board will also discuss pending litigation and may enter executive session.
- Election of officers and administration of oaths of office
- Authorization to accept bid for hunting/fishing lease
- Pay requests totaling over $4 million, including $1.3M for Grand Bayou Floodgate and $1.1M for Hurricane Delta efforts
- Engineering service amendments totaling $710,695.25 for various projects
- Personnel reallocations: Kelly Schouest to MEO-2 and Dominick Lerille to MEO-1 Heavy