South Lafourche Levee District Board of Commissioners public meetings in 2025
12 substantive meetings from 2025, with official agendas or minutes and plain-English summaries.
South Lafourche Levee District Board of Commissioners
The South Lafourche Levee District Board of Commissioners will hold a public meeting to receive reports on levee maintenance, floodwall repairs, and engineering projects. Key updates include pay applications for levee improvements, bid results for hunting and fishing leases, and an intergovernmental agreement for lock operations. The board will also review pending litigation and approve invoices.
- Bid Opening Results – Hunting & Fishing Lease
- IGA with GPLC for Lock Operations, 2026 to 2030 ($ amount not specified)
- Larose Floodwall Pilings Impact & Repair – Request for Quotes
- Pay Application No. 19: $167,400.73 for Larose 'Ted Gisclair' Lock
- Pay Application No. 14: $48,875.00 for Section E - North Levee Improvements
South Lafourche Levee District Board of Commissioners
The South Lafourche Levee District Board of Commissioners will meet to receive reports on levee repairs, equipment purchases, and intergovernmental agreements. The board will also review and approve invoices for ongoing construction projects and discuss employee evaluations and health premiums for 2026.
- Intergovernmental Agreement with CPRA for Barataria Landbridge Project
- Purchase of Ford F-250 (State Contract) for $—
- Purchase of Finn T60 Hydro-Seeder for $—
- Application for Payment No. 18: $207,333.27 to Construction Site Specialties
- Application for Payment No. 13: $45,975.00 to Compeaux & Sons
South Lafourche Levee District Board of Commissioners
The South Lafourche Levee District Board will vote on several construction pay applications, including $141,858.74 for the Ted Gisclair Lock project and $201,082.50 for B-North & B-South levee maintenance. The board will also discuss a sheet pile bid, purchase of sheet piles, sale of a surplus boat trailer, and the 2026 capital outlay request. Other items include approval of Amendment No. 1 to an intergovernmental agreement for the Ted Gisclair Lock and review of 2025 employee health insurance.
- Pay Application No. 17 for $141,858.74 to Construction Site Specialties for Ted Gisclair Lock
- Pay Application No. 12 for $74,362.50 to Compeaux & Sons for Section E levee improvements
- Pay Request for $201,082.50 to Compeaux & Sons for B-North & B-South levee maintenance
- Approval of Amendment No. 1 to IGA BA-0259 for Ted Gisclair Lock
- Review and approve payments for 2026 employee health insurance premiums
South Lafourche Levee District Board of Commissioners
The South Lafourche Levee District will meet on September 2, 2025, to consider multiple pay applications and contract proposals for levee improvement projects, including $23,950 to Compeaux & Sons for Section E-North Levee Improvements and $106,701.97 to GIS Engineering for D-North Ramp Lift. The board will also discuss personnel actions, including filling a Mobile Equipment Operator position and adopting changes to the Personnel Policies & Procedures Manual. An executive session on pending litigation is possible.
- Pay Application No. 11 for $23,950.00 to Compeaux & Sons for Section E-North Levee Improvements
- Pay Application No. 4 for $106,701.97 and Change Order No. 3 for $42,135.00 for D-North Ramp Lift
- Pay requests totaling $105,255.00 to NEWGEM Construction and Compeaux & Sons for B-North & B-South Levee Maintenance
- Contract proposals for A-West Levee Improvements and E-North Levee Improvements
- Possible executive session on pending litigation (Jason Adams, et al v. SLLD and LA Contracting Enterprise, LLC v. SLLD)
South Lafourche Levee District Board of Commissioners
The South Lafourche Levee District will meet on August 11, 2025, to discuss and potentially approve several engineering contracts and payments, including a $59,992.50 pay application for Section E North Levee Improvements. The board will also hear updates on USACE risk assessment, sheet pile purchases, debris monitoring contract extension, and Reach L levee maintenance. Legal matters include pending litigation, with possible executive sessions.
- Pay Application No. 10 for $59,992.50 to Compeaux & Sons for Section E North Levee Improvements
- Pay Application No. 3 for $17,733.27 to Onshore Materials for D-North Ramp Lift
- Pay Application No. 6 for $49,677.13 to Sealevel for D-South Floodwall Phase III Improvements
- Invoices totaling $194,422.50 from NewGem and Compeaux & Sons for B-North & B-South Levee Maintenance
- Approval to add boat trailer (Inv#297) to surplus equipment and advertise for sale
South Lafourche Levee District Board of Commissioners
The board will consider renewing a debris removal contract with Dynamic Group and approving pay applications for levee improvements, including $72,195 to Compeaux & Son and $104,557.38 to Construction Site Specialties. Members will also discuss authorizing the president and executive director to represent the board at arbitration in a pending lawsuit. The meeting includes reports on coastal projects, permits, and a possible executive session on litigation.
- Renewal of Debris Contract – Dynamic Group
- Pay Application No. 9 for $72,195.00 to Compeaux & Son for Section E levee improvements
- Pay Application No. 16 for $104,557.38 to Construction Site Specialties for Section E levee improvements
- Authorization for President & Executive Director to represent Board at Arbitration and negotiate settlement in LA Contracting Enterprise, LLC v. SLLD
- Approval to advertise RFP for Pre-Positioned Post-Disaster Equipment Contractors
South Lafourche Levee District Board of Commissioners
The South Lafourche Levee District Board will consider approving multiple construction pay applications, including $83,966.04 for Section E-North levee improvements and $65,065.00 for Compeaux & Sons. They will also vote on purchasing a 750P crawler dozer for $350,382.38, two F250 pickups totaling $114,731.44, and adopting an amended FY2025 budget. The meeting includes reports on hurricane season preparations, a revised emergency operations manual, and several new engineering contracts.
- Pay Application No. 15 for $83,966.04 to Construction Site Specialties for Section E-North levee improvements
- Pay Application No. 8 for $65,065.00 to Compeaux & Sons Construction for Section E-North levee improvements
- Purchase of 750P crawler dozer on state contract for $350,382.38 plus optional $2,245.50 extended warranty
- Purchase of one F250 pickup with tool panels for $63,045.03 and one F250 pickup for $51,686.41
- Adoption of amended FY2025 budget
South Lafourche Levee District Board of Commissioners
The South Lafourche Levee District will consider approving an intergovernmental agreement (IGA TE-0180) for $4.4 million in construction funds for the A-West project. The board will also vote on IGA amendments and fund transfers for other levee projects, and hear reports on hurricane preparedness, engineering updates, and pending litigation.
- Approval of IGA TE-0180 (A-West) for $4.4M in construction funds
- Approval of IGA BA-0231 (E-North), Amendment No. 6
- Approval of IGA BA-0273 (A-East) to move funds from D-North Ramp
- Pay applications: $11,662.20 to Construction Site Specialties, $68,025.00 to Compeaux & Sons, $45,695.00 to Onshore Materials, $46,977.50 to Sealevel
- Update on pending litigation: Jason Adams, et al v. SLLD and LA Contracting Enterprise, LLC v. SLLD
South Lafourche Levee District Board of Commissioners
The South Lafourche Levee District board will consider and adopt Resolution 2025.01 setting millage rates for 2025 and approve the FY2026 financial budget. They will also review engineering reports, including pay applications and change orders for levee and floodgate projects, and discuss personnel policies, salary adjustments, and pending litigation.
- Consider and adopt Resolution 2025.01 for 2025 millage rates
- Acceptance of FY2026 Financial Budget
- Pay Application No. 6 for $78,015.00 to Compeaux & Sons for Section E North Levee Improvements
- Balancing Change Order No. 2 for ($31,367.93) and Pay Application No. 7 for $57,881.61 on Breton Canal reconnection
- Employee physicals added as condition of hiring and salary adjustments
South Lafourche Levee District Board of Commissioners
The South Lafourche Levee District will meet to discuss engineering reports, including pay applications for levee improvements. Notable items include a $58,695 payment for Section E-North Levee work and a $90,278.74 payment for reconnecting Breton Canal to Bayou Lafourche. The board will also consider filling two vacant positions and revising personnel policies.
- Pay Application No. 5 for $58,695 to Compeaux & Sons for Section E-North Levee Improvements
- Pay Application No. 6 for $90,278.74 to Garden Environments for Breton Canal reconnection
- Pay Application No. 3 for $223,076.63 to Sealevel Construction for D-South Floodwall Phase III
- Proposed FY2026 Budget discussion
- Permission to fill Grass Cutter and Tractor Operator positions
South Lafourche Levee District Board of Commissioners
The South Lafourche Levee District Board of Commissioners will discuss several levee and floodgate improvement projects. The meeting includes reviews of pay applications for construction work and proposals for consulting services.
- Pay Application No. 2 for D-South Floodwall at Crawfish Farms, Phase III Improvements: $166,744.87
- Pay Application No. 13 for Section E-North Levee Improvements: $126,266.68
- Pay Application No. 1 for A-East Interim Levee Improvements: $87,383.25
- Annual membership dues for Restore or Retreat: $500
- Approval to advertise the sale of a surplus excavator
South Lafourche Levee District Board of Commissioners
The Board of Commissioners will discuss levee improvements, pump station renaming, and a water monitoring system agreement. The meeting includes the election of officers and reviews of several engineering project pay applications.
- Pay Application for Section E-North Levee Improvements to Construction Site Specialties for $294,974.31
- Pay Application for D-South Floodwall at Crawfish Farms to Sealevel Construction, Inc. for $230,035.38
- Pay Application for Breton Canal reconnection to Garden Environments, Inc. for $164,617.42
- Authorization for Picciola & Associates to prepare the 2025 Centerline Survey
- Change Order No. 1 for steel sheet piling at D-South Floodwall for $56,092.50