Clinton public meetings in 2023
7 substantive meetings from 2023, with official agendas or minutes and plain-English summaries.
Clinton City - Request for Proposal (RFP)
Clinton City, along with Clearfield City and Weber Basin Water Conservancy District, is seeking prequalification proposals from contractors for the 800 North Roadway & Water Line Project from 450 W to 1000 W. The project includes roadway reconstruction, water line installation, and bridge work. Proposals are due by October 20, 2023.
- Prequalification proposals due October 20, 2023, for 800 North Roadway & Water Line Project
- Joint project with Clearfield City and Weber Basin Water Conservancy District
- Installation of approximately 2,000 linear feet of 12-inch PVC culinary water line and 1,600 linear feet of 8-inch PVC culinary water line
- Horizontal directional drilling under UTA and UPRR tracks at 500 West and UTA box culvert near 950 West
- Replacement of asphalt pavement for approximately 0.6 miles of roadway
Clinton City - Request for Proposal (RFP)
Clinton City is requesting bids for the construction of a Public Safety Building Expansion Project, which includes an approximately 45 ft by 48 ft expansion to existing public safety buildings and remodeling of areas in the existing Fire and Police stations. Bids will be received at Clinton City Hall until August 31, 2023 at 2:00 pm, at which time they will be publicly opened and read. A pre-bid conference is scheduled for August 15, 2023 at 2:00 pm at the same location.
- Construction of approximately 45 ft by 48 ft expansion to public safety buildings
- Remodeling of areas in existing Fire and Police stations
- Bids due August 31, 2023 at 2:00 pm at Clinton City Hall, 2267 North 1500 West, Clinton, UT
- Pre-bid conference on August 15, 2023 at 2:00 pm
- Project # CLINTON2023-1, documents available on Utah Public Procurement Place website
Clinton City - Request for Proposal (RFP)
Clinton City Corporation is requesting bids for the construction of the 1800 North Safe Sidewalk Project. The work includes installing curb, gutter, and sidewalk, and relocating utilities. Bids are due by July 6, 2023, and the project is expected to be complete by October 15, 2023.
- Bids due July 6, 2023 at 10:00 am at Clinton City Public Works Shop, 1740 N 1711 W
- Project includes curb and gutter installation, sidewalk installation, and utility relocation
- Substantial completion by October 1, 2023; final completion by October 15, 2023
- Bidding documents available on QuestCDN (Project #8565422) starting June 21, 2023
- No bid bond required; no pre-bid conference
Clinton City - Request for Proposal (RFP)
Clinton City Corporation is requesting bids for its 2023 Street Surface Treatment Project, which involves applying crack seal and slurry seal to various streets. Bids are due by July 6, 2023, at 10:00 AM, and will be publicly opened at that time. The project is expected to be substantially complete by October 1, 2023.
- Approximately 6 tons of crack seal application
- Approximately 105,000 square yards of Type II Slurry Seal on various streets
- Bids due July 6, 2023, at 10:00 AM at Clinton City Public Works Shop, 1740 N 1711 W
- Project completion expected by October 15, 2023
- No bid bond required; no pre-bid conference
Clinton City - Request for Proposal (RFP)
Clinton City Corporation is requesting bids for the 2300 North SRTS Project, which involves installing curb, gutter, and sidewalk, and relocating utilities. Bids are due by July 6, 2023, and will be publicly opened at that time. The project is federally funded and must comply with federal labor standards.
- Bids due July 6, 2023 at 10:00 AM at 1740 N 1711 W
- Project includes curb, gutter, and sidewalk installation
- Utility relocation required where in conflict with sidewalk
- Federally funded by Safe Route to School (SRTS) program
- Completion expected by November 1, 2023
Clinton City - Request for Proposal (RFP)
Clinton City Corporation is requesting bids for the 2023 Curb Ramp CDBG Project, which involves removing and replacing concrete pedestrian curb ramps. Bids are due by July 6, 2023, at 10:00 AM, and will be publicly opened and read at that time. The project is funded through a HUD Community Development Block Grant and must comply with federal labor standards, including Davis-Bacon wages.
- Removal and replacement of concrete pedestrian curb ramps
- Bids due July 6, 2023, 10:00 AM at Clinton City Public Works Shop, 1740 N 1711 W
- Project funded by HUD Community Development Block Grant (CDBG)
- Contractor must comply with Davis-Bacon wages and Section 3 requirements
- Lowest responsible bidder will be selected
Clinton City - Request for Proposal (RFP)
Clinton City Corporation is requesting bids for its 2023 Street Reconstruction Project. Bids are due by July 6, 2023 at 10:00 am and will be publicly opened at the Public Works Shop. The project includes storm drain installation, asphalt roadway reconstruction, and concrete sidewalk and curb/gutter work, with substantial completion expected by October 1, 2023.
- Bids due July 6, 2023 at 10:00 am at Clinton City Public Works Shop, 1740 N 1711 W
- Project includes storm drain infrastructure installation
- Reconstruction of asphalt roadways
- Reconstruction of concrete sidewalk and curb/gutter
- Substantial completion by October 1, 2023; final by October 15, 2023