Thu Dec 14, 2023

Stadium and Exposition District Board of Commissioners

✓ Decided: Board approves multiple Superdome and SKC construction contracts and upgrades

The Board approved several change orders and contract amendments for the Superdome Master Plan and Smoothie King Center renovations. Additionally, the Board authorized over $207,000 for repairs and upgrades at the TPC Louisiana Golf Course and Clubhouse.

Thu Nov 16, 2023

Stadium and Exposition District Board of Commissioners

✓ Decided: LSED approves $9.5M for capital projects and various Superdome improvements

The Board approved the encumbrance of $9.5 million for future capital projects and authorized several contract adjustments for the Superdome and Smoothie King Center. The Board also approved a contract with Gensler Sports for a facility assessment of the Smoothie King Center and authorized legal action to enforce roof repair warranties.

Thu Oct 26, 2023

Stadium and Exposition District Board of Commissioners

✓ Decided: LSED approves $3.4M Superdome project increase and $204K concession renovations

The Board approved several funding increases and contracts for the Superdome and Smoothie King Center. This included a significant price adjustment for the Master Plan Project and a contract for concession upgrades. The Board also extended a management agreement for the Westwego Sports Complex.

Thu Sep 28, 2023

Stadium and Exposition District Board of Commissioners

✓ Decided: LSED Board approves Superdome and Smoothie King Center project updates

The Board ratified a Project Development Agreement for Superdome Capital Improvements and approved several construction budget adjustments. It also authorized equipment purchases and architectural services for Smoothie King Center renovations and rejected two bids for a storage project that exceeded the budget.

Thu Aug 24, 2023

Stadium and Exposition District Board of Commissioners

✓ Decided: LSED approves Superdome construction adjustments and Shrine on Airline conversion

The Board approved several funding increases for the Superdome Master Plan and the John Alario, Jr. Sports Complex. It also authorized a development agreement to convert the Shrine on Airline into a multi-sports complex.

Thu Jul 27, 2023

Stadium and Exposition District Board of Commissioners

✓ Decided: LSED approves 2024 budget and multiple Superdome capital project adjustments

The Board approved the 2024 fiscal year budget and authorized several construction contract adjustments for the Superdome and Smoothie King Center. Key actions included approving a $2.3M contract for LED displays and extending a 10-year antenna system agreement.

Thu Jun 22, 2023

Stadium and Exposition District Board of Commissioners

✓ Decided: LSED approves over $526M in revenue bonds

The Board approved the issuance of two series of revenue bonds totaling more than $526 million. Other key actions included awarding a $1.1M HVAC contract for the Superdome and approving several professional service contracts for accounting and legal work.

Thu May 25, 2023

Stadium and Exposition District Board of Commissioners

✓ Decided: LSED approves $19.9M increase for Superdome renovation

The Board approved a price adjustment for the Superdome Master Plan Phase 3b and authorized a contract for HVAC controls at the Alario Center. The Board also approved the completion certificate for gutter replacement at the Alario Center and authorized the Westwego sports complex project.

Thu Apr 27, 2023

Stadium and Exposition District Board of Commissioners

✓ Decided: LSED approves $6.9M Verizon WiFi project and bond issuance authority

The Board approved a $6.9 million contract with Verizon for WiFi integration and authorized the issuance of bonds up to $560 million. Several construction adjustments for the Superdome Master Plan and a $20.56 million contract for the John Alario Junior Sports Complex were also detailed or approved.

Wed Mar 22, 2023

Stadium and Exposition District Board of Commissioners

LSED considers $20.56 million contract for Westwego Sports Complex

The Louisiana Stadium and Exposition District is reviewing several contracts and budget adjustments for the Superdome Capital Improvements Project and the Alario Center. The board is also deciding on a primary construction contract for the Westwego Sports Complex/John Alario Sports Complex Project.

stadiumconstructioncontractssuperdomealario-centerwestwego
✓ Decided: Board approves $20.56M contract for John Alario Jr. Sports Complex

The Board approved several construction and service contracts for the Master Plan Project and the Alario Center. The most significant action was the acceptance of a $20.56M bid for the Westwego/John Alario Jr. Sports Complex. Other approvals focused on facility repairs and specialized inspection services.

Thu Feb 9, 2023

Stadium and Exposition District Board of Commissioners

LSED to vote on $943,195 Superdome project cost increase

The Louisiana Stadium and Exposition District is meeting to approve several facility maintenance appropriations and professional service contracts. The board will consider a budget increase for the Superdome Master Plan Project and a contract extension for concession services.

stadiumscontractsbudgetmaintenancelegal-services
✓ Decided: LSED Board approves $943K Superdome construction increase and other facility repairs

The Board approved several funding requests for facility maintenance and construction, including a price adjustment for the Superdome Master Plan Project. The Board also extended the Sodexo food services contract and hired new special legal counsel.