Terrebonne Levee and Conservation District, LA

Terrebonne Levee and Conservation District public meetings in 2025

25 substantive meetings from 2025, with official agendas or minutes and plain-English summaries.

Wed Dec 17, 2025

Terrebonne Levee and Conservation District

Terrebonne Levee District approves $4.57M levee rehabilitation and $70.8K floodgate paint contract

The Terrebonne Levee and Conservation District will meet on December 17, 2025, to approve key contracts and resolutions, including a $4.57 million levee rehabilitation project and a $70,800.70 floodgate paint purchase. The board will also discuss pending litigation and receive updates on ongoing projects.

levee-rehabilitationflood-controlconstruction-contractspublic-meetinglitigation
✓ Decided: Board awards $4.57M levee rehabilitation contract to Rigid Constructors

The Board approved several project contracts and resolutions, including a $4.57M award for Reach I Levee Rehabilitation. Members also approved financial reports, operating invoices, and substantial completion grants for two rehabilitation projects.

Mon Dec 1, 2025

Terrebonne Levee and Conservation District

District considers over $10 million invoice for HNC Lock Complex

The Terrebonne Levee and Conservation District will review project reports and finance matters. The body is considering several high-value invoices and amendments related to the Houma Navigation Canal Lock Complex.

leveesinfrastructureflood-controlcontractshouma-navigation-canal
✓ Decided: Board approves $10.5M Sealevel invoice and several levee project updates

The Board approved multiple invoices, including a $10.49M payment to Sealevel and a $361,893 payment to APTIM. Members also authorized labor quotes for the Pointe Aux Chenes project and an agreement amendment for the Houma Navigation Canal Lock Complex.

Wed Nov 19, 2025

Terrebonne Levee and Conservation District

District considers levee rehabilitation payments and barge gate repairs

The Terrebonne Levee and Conservation District will review several change orders for levee rehabilitation projects and approve quotes for barge gate sensor replacements. The body will also discuss the 2025 Emergency Contingency Plan and potential litigation in executive session.

leveesinfrastructurecontractsflood-controllitigation
✓ Decided: Board awards $971,231.50 contract for Upper Reach I Rehabilitation Project

The Board approved several levee rehabilitation contracts and change orders, including a major award to Lirette Dirt Services. Members also authorized the 2025 Emergency Contingency Plan and the 2026 meeting schedule.

Wed Nov 12, 2025

Terrebonne Levee and Conservation District

District considers over $38 million invoice for HNC Lock Complex

The Terrebonne Levee and Conservation District will review project updates and finance matters. The body is deciding on several intergovernmental agreements and professional service proposals for levee and water control projects.

leveesinfrastructurecontractsflood-controlbudget
✓ Decided: Board approves over $8.9M in invoices and levee lift agreements

The Board approved several high-value invoices for Sealevel and APTIM and authorized two intergovernmental agreements with the CPRA for the Upper Reach I Levee Lift project. Additionally, the Board approved professional services for office improvements and water control structures.

Wed Oct 15, 2025

Terrebonne Levee and Conservation District

Board to vote on IGA for Eastern Terrebonne Restoration Project

The Terrebonne Levee & Conservation District will consider resolutions and contracts for several flood-protection projects, including the Eastern Terrebonne Restoration Project and Morganza-to-the-Gulf levee work. The board may also enter executive session to discuss pending litigation. Public comments are invited.

leveeflood-protectionmorganza-to-the-gulfeastern-terrebonne-restorationcontractslitigationpublic-comment
✓ Decided: Board approves contracts and resolution for Eastern Terrebonne Restoration Project

The Board approved Resolution 25-028 to execute an IGA with CPRA for the 94-mile Eastern Terrebonne Restoration Project. Related program management and engineering contracts were approved, subject to CPRA approval. The Board also authorized a levee servitude for Reach I and awarded a rehabilitation project to Lirette Dirt Services.

Wed Oct 1, 2025

Terrebonne Levee and Conservation District

Board to vote on $9.9M lock complex invoice and multiple levee project contracts

The board will consider approval of a $9,880,942.47 invoice for the HNC Lock Complex Phase 2, along with several change orders and amendments for levee repair and construction projects. An executive session is planned to discuss pending litigation. Public comments will be heard.

leveeflood-protectioncontractspublic-hearinglitigationcapital-projects
✓ Decided: Board approves $9.8M Sealevel invoice and multiple levee project amendments

The Board approved several high-value invoices, including a $9.8M payment to Sealevel and $295,020.25 to APTIM. Members also authorized multiple change orders and amendments for levee lift and maintenance projects. The board received progress updates on the HNC lock and various Reach projects.

Wed Sep 17, 2025

Terrebonne Levee and Conservation District

Board to vote on $748,714 for two Kubota tractors and $56,242 for bush hogs

The Terrebonne Levee and Conservation District will consider approving two equipment purchases totaling $804,955.46: two Kubota tractors from Ascension Equipment Sales and two bush hogs from Parish Tractor Company. The board will also discuss a $7,289,315 change order for the Reach H3/H2 levee lift project, a $3,634,000 amendment for the HNC Lock Complex Phase 2, and a potential executive session on pending litigation. A resolution authorizing a cooperative endeavor agreement with the state for a district office building and possible consent agreements with the EPA for Reach A emergency levee projects are on the agenda.

leveeequipmentcontractscapital-projectslitigationhcn-lock
✓ Decided: Board approves $7.29M change order for Reach H2/H3 Levee Lift

The Board approved several equipment purchases and project amendments, including a significant funding increase for the Reach H2/H3 Levee Lift. Other actions included authorizing a CEA with the State of Louisiana and approving professional services for the HNC Lock Complex.

Wed Sep 3, 2025

Terrebonne Levee and Conservation District

Board to vote on $6.9M HNC Lock invoice and multiple emergency repair change orders

The board will consider approving two large invoices for the HNC Lock Complex Phase 2 project, totaling over $7.2 million, and several final balancing change orders for Hurricane Francine emergency scour repairs. They may also enter executive session to discuss pending litigation and vote on an encroachment agreement for the Morganza to the Gulf project.

✓ Decided: Board approves $6.9M Sealevel invoice and multiple levee repair change orders

The Board approved several high-value invoices and a bid for the Reach L Rehabilitation project. Members also authorized multiple balancing change orders for Hurricane Francine emergency scour repairs and an encroachment agreement with Harvest Midstream.

Wed Aug 20, 2025

Terrebonne Levee and Conservation District

District considers $425,197.67 change order for HNC Lock Complex

The Terrebonne Levee and Conservation District will review capital project updates and financial reports. The body is deciding on several project completions, a security agreement with the Sheriff's Office, and contract change orders.

leveesinfrastructurecontractsflood-controlpublic-safety
✓ Decided: Board approves security agreement with Sheriff's Office and multiple levee project updates

The Board approved an intergovernmental agreement with the Terrebonne Parish Sheriffs Office for security and storm assistance. Members also authorized several construction change orders and granted substantial completion for hurricane scour repairs. A new engineering contract for the Bush Floodgate Dry Dock was approved.

Wed Aug 6, 2025

Terrebonne Levee and Conservation District

Board to vote on $8.9M Sealevel invoice for Houma Navigation Canal Lock Phase 2

The Terrebonne Levee & Conservation District board will consider approving a $8,908,487.87 invoice from Sealevel for Phase 2 of the HNC Lock Complex, along with other invoices and contract awards totaling over $4.3 million for levee maintenance and emergency repairs. The board may also enter executive session to discuss pending litigation.

✓ Decided: Board approves $8.9M Sealevel invoice and multiple levee repair contracts

The Board approved several high-value invoices and awarded multiple maintenance and emergency rehabilitation contracts for levee reaches. It also authorized new fiscal agents and approved project amendments and change orders.

Wed Jul 16, 2025

Terrebonne Levee and Conservation District

Board to vote on $21,445 change order for HNC Lock Complex and multiple contract amendments

The Terrebonne Levee & Conservation District will consider approving several engineering contract amendments and change orders, including a $21,445 change order for the HNC Lock Complex Phase 2 and a final balancing change order of ($129,465.46) for Reach L Segment 1. The board may also enter executive session to discuss pending litigation.

✓ Decided: Board declares emergency for Reach B and Lower Dularge East levee elevations

The Board approved Resolution 25-022 to declare an emergency based on updated centerline surveys for Reach B and Lower Dularge East. Members also approved several project amendments, change orders, and financial reports.

Wed Jul 9, 2025

Terrebonne Levee and Conservation District

Levee board to vote on $9.5M in lock contracts and budget.

The Terrebonne Levee Board will consider approving a $362,258.75 APTIM invoice and a $9,173,744.81 Sealevel invoice for the HNC Lock Complex Phase 2 project, plus a $129,582.00 change order for Reach J-3 and a $324,038.75 change order for Reach K, both related to Hurricane Francine-FEMA work. The board will also vote on the amended FY 2025 budget and the proposed FY 2026 budget, and may enter a closed executive session to discuss three pending lawsuits.

✓ Decided: Board approves $939,584 change order for Reach H3 Levee Project

The Board approved a change order for Rigid Constructors LLC to alter the embankment delivery method for the Reach H3 Levee Project. The Board also approved advertising bids for embankment supply to Reach I Levee.

Fri Jun 27, 2025

Terrebonne Levee and Conservation District

Board to vote on $939,584 change order for Reach H Levee due to bridge closure

The Terrebonne Levee and Conservation District Board will consider a $939,584 change order for Rigid Constructors, LLC on the Reach H3 Levee Project, switching embankment delivery from hauled-in to barged-in because the Boudreaux Canal Swing Bridge is closed. The board will also authorize advertising bids for indefinite embankment supply to Reach I Levee.

✓ Decided: Board approves $939,584 change order for Reach H3 Levee Project

The Board approved a change order for Rigid Constructors LLC to alter the embankment delivery method for the Reach H3 Levee Project. The Board also approved advertising bids for embankment supply for the Reach I Levee.

Wed Jun 18, 2025

Terrebonne Levee and Conservation District

District to hold public hearing on proposed FYE June 30, 2026 budget

The Terrebonne Levee and Conservation District will hold a public hearing regarding the proposed budget for the fiscal year ending June 30, 2026. The body will also consider budget amendments for the current fiscal year and review several levee and floodgate project updates.

budgetleveesflood-controlinfrastructurepublic-hearing
✓ Decided: Board approves $12.6M Sealevel invoice and multiple levee project change orders

The Board approved several high-value invoices, including a $12.6M payment to Sealevel and a $334,529.21 payment to APTIM. Members also authorized various change orders for levee rehabilitation and repair projects and extended a hurricane response contract. The 2025 Amended and 2026 Proposed Budgets were tabled for adoption at the June 18, 2025, meeting.

Wed Jun 4, 2025

Terrebonne Levee and Conservation District

Board to vote on $12.6M HNC Lock Complex Phase 2 invoice and $334,529 APTIM invoice

The Terrebonne Levee & Conservation District will consider approving two large invoices for the HNC Lock Complex Phase 2 project: one from APTIM for $334,529.21 and one from Sealevel Construction for $12,636,023.37. The board will also vote on an amended budget for the current fiscal year and a proposed budget for FYE June 30, 2026, as well as insurance renewal proposals from Arthur Gallagher and USI. Additionally, the board may enter executive session to discuss pending litigation and will consider several change orders and resolutions for levee and floodgate projects.

✓ Decided: Board approves encroachment agreement with Discovery Gas Transmission, LLC

The board approved the April 30, 2025, financial report and operating and engineering invoices. An encroachment agreement with Discovery Gas Transmission, LLC for the Morganza to the Gulf Reach L Levee and Floodwall was authorized. Management and consultants provided updates on various levee and floodgate projects.

Wed May 21, 2025

Terrebonne Levee and Conservation District

District considers encroachment agreement with Discovery Gas Transmission, LLC

The Terrebonne Levee and Conservation District will review project updates and financial reports. The body will consider authorizing an encroachment agreement for the Morganza to the Gulf Reach L Levee and Floodwall Project.

leveesflood-controlinfrastructurelitigationcontracts
✓ Decided: Board approves $9M Sealevel invoice and multiple levee project contracts

The Board approved several high-value invoices and intergovernmental agreements for levee lift projects. Multiple change orders for construction costs and time extensions were approved for various reach segments and lock complexes. The board also awarded a concrete mattress materials bid to Premier Concrete Products, Inc.

Wed May 7, 2025

Terrebonne Levee and Conservation District

Board to vote on $9M+ in levee contracts and intergovernmental agreement

The Terrebonne Levee and Conservation District will consider approving over $9 million in invoices for the HNC Lock Complex Phase 2, including a $9.07 million Sealevel invoice and a $337,841.47 AECOM invoice. The board will also vote on an intergovernmental agreement with the state for the Reach H3/H2 Levee Lift project, a $518,100 contract for concrete mattress materials, and several change orders for ongoing levee and floodgate projects.

leveeflood-protectioncontractscoastal-restorationinfrastructurepublic-meeting
✓ Decided: Board awards over $11M in levee and floodwall construction contracts

The Board approved several major construction awards for floodwall and levee improvements funded by the CPRA. It also authorized funding amendments for engineering services and granted substantial completion for two projects. Other actions included approving financial statements and maintenance change orders.

Wed Apr 16, 2025

Terrebonne Levee and Conservation District

Board to vote on $7.5M floodwall and $3.8M levee lift contracts

The Terrebonne Levee & Conservation District will consider awarding two major construction contracts: $7,470,637.50 to Sealevel Construction for a floodwall structure and $3,799,999.00 to Rigid Constructors for levee improvements. The board will also vote on a $2.5 million amendment for the Houma Navigational Canal Lock Complex project and a resolution granting substantial completion for the Lower Dularge East Levee Rehabilitation. An executive session is planned to discuss pending litigation.

✓ Decided: Board approves $7.8M Sealevel invoice and $1.9M aggregate materials contract

The Board approved several high-value invoices and contracts, including a $7.8M payment to Sealevel and a $1.9M agreement for aggregate materials. Members also granted substantial completion for two levee projects and approved multiple change orders for site and repair work.

Wed Apr 2, 2025

Terrebonne Levee and Conservation District

Board to vote on $7.8M Sealevel invoice and $1.9M aggregate materials bid

The Terrebonne Levee & Conservation District will consider approving a $7,831,628.98 Sealevel invoice for HNC Lock Complex Phase 2, a $1.9 million annual aggregate materials bid, and several other contracts and change orders for levee and floodgate projects.

✓ Decided: Board approves financial statements and levee project change orders

The Board approved the February financial statements and operating and engineering invoices. Two change orders for floodgate and barge gate maintenance were approved to extend contract timelines.

Wed Mar 19, 2025

Terrebonne Levee and Conservation District

Board to discuss litigation and consider change orders for floodgate projects

The Terrebonne Levee & Conservation District Board will consider approving operating and engineering invoices, a financial report, and change orders for floodgate improvements. The board may also enter executive session to discuss pending litigation, including cases involving Kathleen Powell and Dewey Aucoin against the State of Louisiana.

✓ Decided: Board approves $7.7M Sealevel invoice and 2025 millage rate

The Board approved several large project payments, including a $7.7M invoice for Sealevel and a $270,419.50 invoice for Aptim. Members also passed the 2025 millage rate and granted project completions for levee rehabilitation and scour repair. Additional approvals were made for maintenance contracts and FEMA-reimbursable services.

Wed Mar 12, 2025

Terrebonne Levee and Conservation District

Board to set 2025 tax rate, vote on $7.7M lock invoice

The Terrebonne Levee & Conservation District will vote on Resolution 25-005 to adopt the 2025 millage rate and consider approval of a $7,706,987.34 Sealevel invoice for the HNC Lock Complex Phase 2. The board will also discuss potential executive session on four pending or potential litigation cases, and consider resolutions for project completion and a $1.5M+ paint quote for the Bayou Petit Caillou Barge Gate.

✓ Decided: Board approves 3% cost of living increase for hourly employees

The Board approved a cost of living increase for hourly staff and authorized several project payments and contract amendments. They also approved the surplus of a marsh buggy and the purchase of aggregate for Sweet Pond Road.

Wed Feb 19, 2025

Terrebonne Levee and Conservation District

Board to vote on paint quote for PAC Barge Gate, possible surplus of marsh buggy, and 3% cost-of-living raise

The Terrebonne Levee & Conservation District will consider approving a $23,188.36 paint quote for the PAC Barge Gate, declaring Unit #53 (a 2017 CAT330F marsh buggy) as surplus, and hauling 1,800 tons of #610 aggregate to Sweet Water Pond Access Road. The board will also vote on a 3% cost-of-living adjustment for hourly employees, ratify opening a Regions checking account for a grant, and discuss potential litigation in executive session. Additionally, they will consider Resolution 25-003 for final acceptance of the Bayou Grand Caillou Floating Barge Gate resurfacing project and Amendment No. 3 with T. Baker Smith for the Lower Reach I Levee Lift Phase I.

✓ Decided: Board approves $3.8M Sealevel invoice and levee project change orders

The Board approved a $3,819,162.78 invoice for Sealevel and various operating and engineering invoices. Two contract increases for Onshore Materials, LLC were approved for levee rehabilitation projects. A no-cost change order for Hurricane Francine yardage reclassification was also passed.

Wed Feb 5, 2025

Terrebonne Levee and Conservation District

Board to vote on $3.8M lock complex invoice and approve $1.6M in levee repair change orders

The Terrebonne Levee and Conservation District will consider approving a $3,819,162.78 invoice for the HNC Lock Complex Phase 2 and two change orders totaling $1,611,152.74 for levee rehabilitation projects. The board may also enter executive session to discuss pending litigation. This meeting is a regular public meeting with decisions on contracts and project updates.

leveeconservationcontractslitigationflood-protection
✓ Decided: Board awards $1.06M contract for Hurricane Francine emergency scour repair

The Board approved several levee project change orders and emergency repair contracts. It also authorized payments for APTIM and engineering invoices and approved the December 2024 financial report.

Wed Jan 29, 2025

Terrebonne Levee and Conservation District

District to consider $1 million contract for Hurricane Francine repair project

The Terrebonne Levee and Conservation District will review several levee rehabilitation projects and engineering amendments. The agenda includes reviewing invoices for the HNC Lock Complex and discussing pending litigation in executive session.

leveeinfrastructurecontractshurricane-recoveryfinance
✓ Decided: Board approves $6.5M Sealevel invoice and multiple levee project actions

The Board approved several large invoices, including $6.5M for Sealevel and $231,064.25 for APTIM. Members passed resolutions for project acceptance, state treasury agreements, and intergovernmental data sharing. The Board also approved two contract change orders for time and labor repairs.

Wed Jan 15, 2025

Terrebonne Levee and Conservation District

District considers over $6.7 million in HNC Lock Complex invoices

The Terrebonne Levee and Conservation District will review project updates and financial matters. The body is considering several invoices for the Houma Navigational Canal Lock Complex and discussing potential litigation and intergovernmental agreements.

leveesinfrastructurecontractsflood-controlhouma-navigational-canal
✓ Decided: Board awards $2.9M for Hurricane Francine emergency repairs

The Board approved several levee improvement contracts and change orders, including a major award for emergency repairs. They also authorized the advertisement of two new levee and bridge projects. Financial reports and various project invoices were approved.