Board of Supervisors
The Board of Supervisors approved a claims docket totaling $1,625,677 and multiple payments for county-wide road overlay and walking trail resurfacing. The Board also authorized a rental agreement with Canon USA and approved several Sheriff's Department personnel changes.
- Approved Claims Docket for December 21, 2022 totaling $1,625,677 (4-0)
- Approved $655,701.91 and $107,780.53 payments to Huey P. Stockstill, LLC for County Wide Overlay (4-0)
- Approved walking trail resurfacing payments to Warren & Warren Asphalt Paving, LLC for Carriere ($33,282.48), Henleyfield ($34,089.36), and McNeill ($34,561.68) (4-0)
- Approved User Agreement and $1,225.00 payment to Virtual Academy for Sheriff's Department (4-0)
- Approved Sheriff's personnel changes including hiring Jenifer McGinnis and retirements of Mitchell Garriga, Robin Smith, and Lisa Wayne (4-0)
- Authorized Board President to execute rental agreement with Canon USA, Inc. (4-0)
- Approved petitions for increases and reductions of real and personal assessments (4-0)
- Approved amendments to 2022 Homestead Applications (4-0)
Board of Supervisors
The Board of Supervisors approved the demolition of an old circle crane and the sale of resulting surplus property. They also approved several personnel changes for the Sheriff's Department and Central Dispatch, as well as various project payments and permit reimbursements.
- Awarded old circle crane demolition to Demolition & Recycling, LLC for $3,501 payment to County (5-0)
- Approved $19,792.50 payment to Magco, Inc. for MSU Extension Building Site Development (5-0)
- Approved $239,123.55 payment to Hanco Corporation and $3,347.73 to Landry Lewis Germany Architects for Courthouse Renovations (5-0)
- Approved Sheriff's personnel changes: Tania Lucas to Patrol Deputy and resignation of Chajuana Gibson (5-0)
- Approved seizure of $3,175.00 from Darren James Baham and three weapons from Clay Obrien Hodge (5-0)
- Approved hiring of Meagan J. Calhoun and Aubrey N. Smith as Dispatchers (5-0)
- Approved $702.90 building permit reimbursement for Joseph Garcia and $25.00 electrical permit reimbursement for John Meyers (5-0)
- Approved Claims Docket for December 5, 2022 (5-0)
Board of Supervisors
The Board approved several equipment purchases for the Nicholson Volunteer Fire Department to replace items lost in a fire and authorized bids for new IT infrastructure and a server upgrade. Personnel changes in the Sheriff's Department were approved, and the Road Department was authorized to install dangerous intersection signs.
- Approved Claims Docket for November 16, 2022 (5-0)
- Approved Sheriff's personnel changes: Christopher Simmons to Transport Officer and hire of Terold Martin, Sr. as Correctional Lieutenant (5-0)
- Authorized Road Department to install dangerous intersection signs at Hwy 11 and McNeill Henleyfield Road (5-0)
- Approved $5,925.00 for Nicholson VFD turnout gear from Municipal Emergency Services (5-0)
- Approved $8,328.11 for Nicholson VFD turnout gear from A-1 Fire Equipment (5-0)
- Approved $18,463.82 for Nicholson VFD miscellaneous equipment from A-1 Fire Equipment (5-0)
- Authorized $49,000.00 purchase of 1999 Pierce Pumper for Nicholson VFD from Deep South Fire Trucks (5-0)
- Approved $15,000.00 90-day truck rental for Northeast VFD from Deep South Fire Trucks (5-0)
Board of Supervisors
The Board of Supervisors approved several infrastructure payments, including a $247,525.12 overlay project and a $143,023.72 building site development. They also authorized the purchase of three Ford F-150s for the Sheriff's Department and approved a contract for an alcohol and drug program instructor.
- Approved purchase of (3) 2022 Ford F-150 Crew Cab 4WD vehicles for $114,945 (5-0)
- Approved $247,525.12 payment to Huey P. Stockstill for County Wide Overlay Application No. 5 (5-0)
- Approved $143,023.72 payment to Magco, Inc. for MSU Extension Building Site Development Application No. 2 (5-0)
- Approved $66,643.12 final payment to Clymer Contracting, LLC for Riding Arena Expansion Project (5-0)
- Awarded Walking Trail Paving Project for Carriere, Henleyfield, and McNeill to Warren & Warren Paving, LLC (5-0)
- Approved $1,500 monthly contract for Jimmy Richardson as Alcohol and Drug Program instructor (5-0)
- Approved bridge replacement project LSBP-55(38) for Charlie Daughdrill Road (5-0)
- Approved Claims Docket for November 7, 2022, totaling $1,674,505 (5-0)