Fri Dec 16, 2022

Planning Commission

✓ Decided: Planning Commission approves multiple site plans and residential plats

The Commission approved several site plans and residential subdivision plats subject to staff recommendations. Three rezoning and development requests, including the Leeward Estates project, were deferred to January 2023. The 2023 meeting calendar was also adopted.

Thu Dec 15, 2022

Board of Zoning Appeals

✓ Decided: Board of Zoning Appeals approves multiple variances and short-term rental renewal

The Board approved several requests for road frontage, height, and setback variances, as well as a short-term rental renewal. One request for two dwellings on a single tract was denied. The 2023 meeting calendar was approved for six months.

Fri Nov 18, 2022

Planning Commission

✓ Decided: Planning Commission approves land use amendment and rezoning for Lone Oak Road property

The Commission approved a land use plan amendment and rezoning for 60.74 acres at 2525 Lone Oak Road, forwarding both to the County Commission. A rezoning request for 89.61 acres on McCrary Road was deferred. Several site plans and plats were also approved.

Thu Nov 17, 2022

Board of Zoning Appeals

✓ Decided: Board of Zoning Appeals rules on short-term rentals and property variances

The Board approved several short-term rental requests and building permit extensions. Multiple requests for short-term rentals and a wedding venue were denied based on acreage requirements or state exemptions. Several property setback variances were also granted or denied.

Fri Oct 21, 2022

Planning Commission

✓ Decided: Planning Commission approves rezoning for LaGuardo Utility District

The Wilson County Planning Commission approved a rezoning request from Rebecca H. Shaffer for property at 355 Woods Ferry Road, changing it from Agricultural (A-1) to Highway Commercial (C-3). The request will be forwarded to the Wilson County Commission for final approval. Several site plans and plats were also approved, including a trucking facility on Couchville Pike and a revised site plan for Wilson Commerce Center. One preliminary plat for The Grove @ Bartons Creek was withdrawn by the applicant.